EPC general contractor – contractor for baccarat casino electricity industry, PC1 Group

baccarat casino
Rate this post

PC1 Group Joint Stock Company, which was founded in 1963, has been providing electrical construction and installation services in Vietnam for nearly 60 years. It is currently baccarat casino leading enterprise in baccarat casino field of EPC general contractor for baccarat casino electricity industry in Vietnam and Southeast Asia.PC1 Groupis committed to providing customers with current industrial solutions and electrical work that are of high quality, safe, and cost-effective, all while maintaining industrial aesthetics.

Introducing PC1 Group, an EPC general contractor for baccarat casino electrical industry

PC1 Group Joint Stock Company is Vietnam’s leading electrical general contractor, and baccarat casino contractor of many large projects that have been constructed. Investors who deal with PC1 will get full support in baccarat casino areas of consulting, design, supply, installation, operation, and maintenance. PC1 is dedicated to providing customers with baccarat casino greatest service experience possible, with nearly six decades of experience as an electrical general contractor and more than ten strong member companies.

See more:Professional and prestigious EPC general contractor in Vietnam

baccarat casino importance of power sector projects

Contractor for baccarat casino electricity industry

baccarat casino electricity industry is a critical infrastructure sector that supports socioeconomic development, provides baccarat casino foundation for modern industry development, and encourages scientific and technological progress as well as cultural life. baccarat casino electrical business also helps to industry restructuring, economic recovery and growth, and national defense and security by following baccarat casino motto “electricity is one step ahead.” As a result, our Party and State place a high priority on investing in electricity projects as well as establishing systems and regulations to facilitate their development.

Criteria for selecting a high-quality and reputable EPC general contractor

Criteria for selecting a EPC general baccarat casino

Because power projects, which are major undertakings, are on a national scale, selecting a contractor, a construction unit, or a partner to do baccarat casino same thing is critical to baccarat casino project’s success. This is vitally important for baccarat casino project’s overall success. As a result, baccarat casino selection criteria for an EPC general contractor must be exceedingly stringent. Please see baccarat casino following criteria for evaluating baccarat casino capacity of an EPC contractor in baccarat casino power sector:

  • Registered business in accordance with baccarat casino bidding package’s content
  • Had adequate experience and labor to complete baccarat casino EPC contract’s items.

See more:EPC general contractor requirements

Why should you select PC1 Group as your power industry EPC general contractor?

EPC general contractor for baccarat casino electricity industry

  • PC1 Group is a major EPC general contractor for high and super high voltage electrical projects in Vietnam.
  • With its professional competence and experience in baccarat casino building of large-scale projects, PC1 Group’s traditional intrinsic strength in baccarat casino power industry is general contractor.
  • Control and coordinate baccarat casino design, procurement of materials and equipment, construction, and energizing services stages.
  • ABB, SEIMENS, GE, CG, and other worldwide electrical equipment manufacturers count on us as a key partner.
  • Constantly researching, investing in, and using new technologies to benefit management, operations, and construction in order to boost labor productivity, product quality, professionalism, and worker safety.

PC1 Group’s EPC general contractor projects in baccarat casino electricity industry

2018-2020 period

EPC PC1 is baccarat casino EPC general contractor for legal services, technical design, procurement, construction, development, production, installation, testing, and operation of power plants, as well as COD for power plants of baccarat casino following projects:

Dau Tieng Solar Power Project – 500 MW

  • Investor: Power China Huadong Engineering Corporation Limited
  • Time to complete: June 2018 – March 2019

BIM2, BIM3 solar power project – 300 MWp

  • Investor: BIM Group – AC Energy Group
  • Time to complete: June 2018 – April 2019

Phu My solar power plant project – 330MW

  • Investor: Vision Development Joint Stock Company Charged Energy
  • Time to complete: May 2020 – December 2020

Ninh Phuoc solar power plant project 6.1 & 6.2 – 58.3 MWp

  • Investor: Ninh Thuan Renewable Energy and Agriculture Joint Stock Company
  • Time to complete: December 2018 – June 2019

My Son – Hoan Loc Viet solar power plant project – 50MWp

  • Investor: Hoan Loc Viet Joint Stock Company
  • Time to complete: November 2018 – May 2019

DaMi solar power plant project – 47.5MWp

  • Investor: Power Generation Corporation No.1
  • Time to complete: June 2018 – May 2019

Bach Khoa – A Chau solar power plant project

  • Investor: Sungrow Corporation
  • Time to complete: December 2018 – June 2019

Tri Viet solar power plant project

  • Investor: Sungrow Corporation
  • Time to complete: December 2018 – June 2019

BMT solar power plant project

  • Investor: AC Energy Corporation
  • Time to complete: October 2018 – April 2019

Nhi Ha solar power plant project

  • Investor: Bitexco Energy Joint Stock Company
  • Time to complete: February 2019 – June 2019

Phuoc Thai 1 solar power plant project

  • Investor: Vietnam Electricity Corporation
  • Time to complete: September 2019 – June 2020

Phan Lam 2  solar power plant project

  • Investor: BBG Group
  • Time to complete: June 2020 – November 2020

Project of 110kV-63 MVA Substation Project Dam Nai Wind Power Plant 2

  • Investor: baccarat casino Blue Circle
  • Time to complete: May 2018 – September 2018

Dai Phong Wind Power Plant Project 50MW

  • Investor: Dai Phong Development Investment Joint Stock Company – baccarat casino Blue Circle – AC Energy
  • Time to complete: September 2019 – July 2020

2020-2021 period

Under baccarat casino following projects, EPC PC1 is baccarat casino EPC general contractor for legal services, technical design, procurement, construction, development, production, installation, testing of lines and substations, and COD for power plants.

Korea Wind Power Plant Project – Tra Vinh (V1.1)

  • Investor: Tra Vinh 1 Wind Power Company Limited (TWPC)
  • Time to complete: December 2019 – September 2021

Hanbaram Wind Power Plant Project 1, 2

  • Investor: Hanbaram Wind Power Joint Stock Company
  • Time to complete: January 2021 – September 2021

Hung Hai Wind Power Plant Project – 100MW

  • Investor: Hung Hai Wind Power Joint Stock Company – BBG Group
  • Time to complete: January 2021 – October 2021

IAPet Dak Doa Wind Power Plant Project – 199MW

  • Investor: TREE Group
  • Time to complete: March 2021 – October 2021

PC1 is baccarat casino EPC general contractor for items such as legal services, technical design, procurement, construction, development, production, installation, testing, baccarat casino entire factory, COD for baccarat casino entire power plants under baccarat casino following projects:

Lien Lap Wind Power Plant Project – 48MW

  • Investor: Lien Lap Wind Power Joint Stock Company
  • Time to complete: April 2020 – September 2021

Phong Huy Wind Power Plant Project – 48MW

  • Investor: Phong Huy Wind Power Joint Stock Company
  • Time to complete: April 2020 – September 2021

Phong Nguyen Wind Power Plant Project – 48MW

  • Investor: Phong Nguyen Wind Power Joint Stock Company
  • Time to complete: April 2020 – September 2021

IA Bang 1 Wind Power Plant Project – 50MW

  • Investor: Gia Lai Electricity Joint Stock Company
  • Time to complete: October 2020 – October 2021

Tan Phu Dong Wind Power Plant Project (Nearshore)

  • Investor: Tien Giang Wind Power Joint Stock Company
  • Time to complete: March 2021 – October 2021

See more:List of projects implemented by EPC PC1 Group’s general contractor

Choosing PC1 Group Joint Stock Company – a reputable and quality partner

PC1 baccarat casino - a reputable and quality partner

Over 50 years, PC1 Group has been a pioneer in baccarat casino field of contractor for baccarat casino electricity industry, providing full solutions ranging from design to equipment supply, installation, operation, maintenance, and repair to assure client safety. Thousands of investors across baccarat casino country benefit from optimal performance and greater efficiency. We have a distinct advantage at PC1 in baccarat casino following areas:

  • Over 50 years of experience in baccarat casino sector.
  • A team of specialists, professional consultants, more than ten strong member units, and a 24/7 technical support center.
  • Thousands of systems have been placed across baccarat casino country.
  • Assisting baccarat casino project throughout its life cycle with partners and investors
  • Many domestic and international partners have put their faith in me.
  • There are partners all around baccarat casino world who supply outstanding equipment.

PC1 Group is baccarat casino choice of a valuable and effective EPC general contractor for customers, businesses, and investors in baccarat casino electricity industry. PC1 Group pledges to be “always a trustworthy partner, providing exceptional value to consumers”!

Please contact PC1 Group if you are a customer, a business, or an investor interested in power projects. Today, we are prepared to support you throughout baccarat casino whole project.

See more:PC1 portfolio

PC1 GROUP JOINT STOCK COMPANY

  • Tax code: 0100100745; Ticker symbol: PC1
  • Building CT2-No. 583 Nguyen Trai, Thanh Xuan, Hanoi, VN
  • Solution hotline: 0981.119.120
  • Email: epc@pcc1.com.vn

Leave a Reply

Your email address will not be published. Required fields are marked*